The Greenport Village Board during Monday night's work session. (Credit: Jen Nuzzo)

The Greenport Village Board during Monday night’s work session. (Credit: Jen Nuzzo)

The Greenport Village Board has approved a nearly $55,000 study to review the village’s electrical plant that faulted in August and left some residents with without power for more than 11 hours.

(more…)

10/30/14 2:00pm
10/30/2014 2:00 PM
Greenport Village Hall.

Greenport Village Hall.

Greenport Village officials said “backward wiring” was to blame for an August power outage that left some residents without power for more than 11 hours.

“What we found was that the transformer that feeds into the relay switch gear was wired backward,” village administrator Paul Pallas said during Monday’s meeting.  (more…)