Southold postpones hearing on billionaire Soloviev’s controversial Colusa North Fork development plan
The Southold Town Planning Board has postponed a public hearing on billionaire Stefan Soloviev’s proposed Colusa subdivision until January, saying it needs more time to review the project’s potential environmental impacts.
The hearing on the controversial 372-acre development in Cutchogue and Peconic was moved from Dec. 7 to Jan. 11, 2027, Planning Board Chairman James H. Rich III wrote in a letter to the developer’s attorney, Martin Finnegan, on Friday, Nov. 20.
“The Planning Board initially set the hearing date with the expectation that the State Environmental Quality Review Act (SEQRA) review would be completed beforehand,” Mr. Rich wrote. “However, the Board requires additional time to thoroughly evaluate potential environmental impacts and issue a SEQRA determination, which must occur prior to opening the public hearing.”
The board must decide whether to require a full environmental impact statement. Mr. Rich’s letter did not specify which parts of the review are still outstanding. The town hired Hardesty & Hanover to assist with the review, which it estimated would cost $30,000. Mr. Finnegan submitted a $20,000 initial deposit in May.

The property lies east of Bridge Lane and runs from County Road 48 north to Long Island Sound. The plan, submitted by Soloviev’s Crossroads Atlantic LLC, calls for 47 lots for homes and a beach-access lot.
The revised plans break those 47 into 44 residential lots and three farm development lots. About 267 acres of buildable land are proposed for preservation through a sale of development rights to Southold Town and Suffolk County, according to public records.
Colusa is one of two subdivisions Soloviev’s company is pursuing in Southold, along with a proposal on Oregon Road. A neighboring Pindar-owned vineyard was recently listed for $6 million with its development rights intact, The Suffolk Times exclusively reported last week.
At a Nov. 10 Land Preservation Committee meeting, members asked Mr. Finnegan about road frontage lots that would be reached by long, narrow driveways and whether the remaining parcels would be practical to farm.

“This is pretty clearly the most money you can make from dividing and conquering this farmland, which has been farmland for all of its history,” committee member William Lee said. He added that “it would be nice to see it focus on agriculture rather than the residential aspect of it.”
Town Planning Director Heather Lanza said an earlier version did not comply with the subdivision code because it showed homes and a road cutting through farmland. The developer removed the road through the center of the property, shifted residential lots and divided the main farm into three parcels with designated areas where farmhouses could be built.
In March, Ms. Lanza said the revised plan was better suited to continued farming, and the board accepted it as complete for review.
The application uses Southold’s 75/75 conservation subdivision rules, which require a 75% reduction in potential residential lots and preservation of at least 75% of the buildable land. The applicant estimates that land in active agriculture would fall from about 278 acres to 241 acres.
Southold Town residents Sheila Griffin and Jennifer Wojtas submitted written comments this month asking the board to look more closely at groundwater, wastewater, bluff erosion, traffic and emergency access. They also asked how the farms would be irrigated, citing a county planning staff report that said existing agricultural wells appeared to be concentrated on one parcel.
After the postponement was announced, a Facebook post urged neighbors to submit comments before the board’s Dec. 7 meeting. A separate post highlighted a 2004 covenant covering nearly 10 acres now included in Colusa. The covenant says the property “cannot be further subdivided” and allows the restrictions to be changed with the Planning Board’s written consent.
“Why should a restriction established over 20 years ago be changed, and how would doing so benefit North Fork residents?” the person wrote in the Facebook post.
Town planning staff identified at least one covenant that would need to be amended for Colusa to proceed. The applicant’s engineers said in February that the covenant would be amended. Its current status remains unclear.
The Colusa application estimates the development would use about 14,100 gallons of water a day and generate about as much wastewater. It proposes public water and individual wastewater treatment systems.
The Southold Fire District recommended a 12-inch main off County Road 48, and the Cutchogue Fire District asked whether the water supply could support firefighting during a large incident. Town Trustees recommended an undisturbed buffer at least 100 feet wide inland from the bluff crest on waterfront lots, according to town records.
The Suffolk County Planning Commission voted 9–0 in June to approve the preliminary plan with a condition that the final subdivision map be submitted to the commission before final approval. The application remains under review in Southold.
Ms. Lanza and Mr. Finnegan could not be reached for comment on the postponement.
Formal notice with the date and time of the rescheduled hearing will follow the board’s Dec. 7 meeting, Mr. Rich wrote.